Add other costs and company costs
Record freight, packaging and outside help on a job or a client, and rent, utilities and salaried staff as company costs, with credits as minus amounts.
Money out has four buckets: labor, materials, other costs and time not on a job. Other costs are what a job costs besides labor and material: freight, pallets, packaging, outside help. Leave them out and the job looks better than it is. Company costs are bills that belong to no single job, like rent. They count in company profit, never in a job.
Before you start
- Adding costs needs a manager, admin or owner. Costs are money, so they are hidden from roles that do not see money.
Where a cost can sit
| Level | Example | Where it counts |
|---|---|---|
| A job | Freight in for one job. | In that job's cost and profit. |
| A client, no job | Storage or a shared pallet run for one client. | In the client's profit and cost to serve, not in any job. |
| The whole company | Rent, utilities, equipment, salaried staff, insurance. | Only in company profit, as your real overhead. |
Put each cost in one place only. A supervisor's pay goes either in overhead per hour or in company costs, never both.
Add a cost to a job
- Open the job and go to the Materials tab.
- Under Other costs on this job, select Add costs.
- Type one row per cost, or paste rows from a spreadsheet.
- Save.
You can also start from the job's Overview with Add a cost.
Add company costs or client costs
- Go to More > Settings and open Month close.
- Pick the month.
- Under Entries dated in the month, open the Company costs tab, select Add company costs and type one row per bill.
- For a cost on a client, open the All other costs tab, add the row and pick the client under For.
The columns
| Column | What it holds |
|---|---|
| Date | The day of the cost. |
| For | A job, a client, or The whole company. |
| What for | Freight, Packaging, Equipment, Outside help, Rework, Supplies, Storage, Rent, Utilities, Salaried staff, Insurance or Other. |
| Paid to | Who was paid. |
| Reference | A bill number. |
| Note | Anything worth knowing. |
| Amount | In dollars. Use a minus sign for a credit, like a vendor refund. It cannot be zero. |
Cells edit in place and every change has an undo. The list total adds every row, and a credit takes away from it.
How company costs reach company profit
Company costs are typed by month. For a week or part of a month, Pulse takes a share of the month's costs by day. Settings > Cost rules > Spread company costs by picks Calendar days or Work days. A whole month is the same either way. Pulse then compares the month's company costs with the overhead your hourly rates already covered. See How Pulse does the math.
Worked example (made-up figures)
November company costs are $70,500.00. You look at November 1 to 18 with calendar days.
- Share for 18 of 30 days: $70,500.00 x 18 / 30 = $42,300.00.
- If your hourly rates covered $38,000.00 of overhead on those days, the overhead your hourly rate did not cover is $4,300.00.
Import costs
Use the Costs template. A row with a job number goes on that job, a row with a client code goes on that client, and a row with neither is a company cost. See CSV files and their columns.
Related